Essential Power Support for the Kaiser Permanente Ontario Medical Center using Long Duration Batteries within a Renewable Energy Microgrid

Charge Bliss, Inc.

Recipient

Irvine, CA

Recipient Location

37th

Senate District

73rd

Assembly District

beenhere

$8,120,308

Amount Spent

refresh

Active

Project Status

Project Update

This project is in the last stage of completion. The site construction is complete, and the 9 MWh Eos battery system, transformers and switch gear have been installed on site. Initial "cold" testing began at the end of 2023. The receipt of conditional Permission to Operate (PTO) in 2024 allowed "hot" commissioning and testing to begin. Full PTO was granted in early 2025 as final commissioning activities began.

The Issue

Integration of long-duration energy storage into renewable energy microgrids faces several hurdles. This project will demonstrate the technical and operational viability of a long-duration energy storage (LDES) system, capturing lessons learned to inform best practices and support the broader advancement of the LDES market.

Project Innovation

The project will demonstrate a 10-hour flow battery system combined with solar PV and a microgrid controller to support the Kaiser Permanente Ontario Medical Center. This project builds on a prior project funded by the CEC’s Electric Program Investment Charge (EPIC) program, at a hospital in Richmond, CA and allows a direct performance comparison. The recipient will measure parameters such as energy production, round-trip efficiency, demand reduction, islanding frequency, island duration, and the ability to provide ancillary services. The system will be tested for the ability to serve nearly 100 percent of the hospital’s load for 12-hours or longer. The project team will further develop the microgrid controller to optimize its functions.

Project Goals

Demonstrate the integration of a flow battery system into the normal and emergency power systems of a hospital.
Demonstrate economic benefits of the system for the hospital through peak shaving and ancillary services.
Successfully integrate the existing fuel cell system and new PV solar system into the microgrid.
Managing these resources for maximal savings and safe practices.

Project Benefits

Demonstrate prolonged support of critical hospital power systems using clean energy provided by renewables and energy storage instead of fossil fuel-based diesel generators.

Demonstrate the performance difference between long-duration flow batteries when compared to lithium-ion systems in terms of safety, operation and environmental factors

Demonstrate the value of a next generation microgrid controller with automated demand response (ADR) for clean energy technology capabilities when compared to the manual operation of fossil fuel diesel generation systems.

Lower Costs

Affordability

The system will annually produce up to 4.1 GWh of clean renewable energy or 123 GWh over its lifetime. This translates to an estimated annual savings of $328,000 or $9.84 million over the lifetime of the system. Peak load reductions are estimated to provide additional financial benefits.

Environmental & Public Health

Environmental Sustainability

This project represents a major step toward cleaner energy systems by establishing a hospital backup configuration in which the microgrid serves as the primary backup resource, with diesel generation used only if needed.

Key Project Members

Project Member

Mark Handy

COO
Project Member

Steve Gabbitas

Assistant Project Manager

Subrecipients

Rocket

Charge Bliss Construction California, Inc. DBA Faraday Microgrids

Rocket

Mazzetti, Inc.

Rocket

DC Energy Services

Rocket

Golden State Power, LLC

Rocket

ConTech CA

Rocket

Troy Brown Consulting

Rocket

Nhu Energy, Inc

Rocket

KPC Group

Rocket

Match Partners

Rocket

Charge Bliss, Inc.

Rocket

Charge Bliss Construction California, Inc. DBA Faraday Microgrids

Rocket

Kaiser Permanente National Facilities Services

Rocket

Contact the Team

*Required